Revamping of Raffineria Eni Sannazzaro

  • Customer: Raffineria Eni Sannazzaro – 2011
  • Locations: Italy
  • Scope of Work: Convection sections fabricated and delivered in modules. Radiant sections fabricated and delivered to site in panels (refractory lining included). Engineering study to allow the erection of the whole heater on temporary plinths near to its final location in the plant and the transport through special trolleys
  • Year of Contract Award: 2011
  • Year of Construction: 2011
  • Type of heater: Vacuum Heater B-5702
  • Schedule of Execution: 7 months
  • Total time for Engineering: 3,5 months
  • Total Time for Procurement, Fabrication, Delivery to site: 6 months
  • Duration of erection on temporary lay-down area: 4 months
  • Duration of Furnace substitution and start-up: 30 days
  • Total Home Office hours: 4200
  • Fabricated by: Anors
  • Erection by: Tecnoplant
  • Trolley by: Fagioli SpA
  • Average manpower: about 35 workers during the revamping (around 30.000 hours)
  • Weight of handled materials: 500 Tons